In Madhya Pradesh, deep cracks have developed on a 100 metre stretch on the one-month-old Lebad-Mhow four-lane road near Pithampur, a large part of which is still under construction.
The commuters are facing severe problems due to barricades placed on both sides of the road by the company undertaking the project.
Eyewitnesses in Vishwas Nagar colony of Pithampur, said deep cracks have been developed on the newly constructed road. They reported the matter to the Mhowgaon police post of Kishanganj police station. Dilip Buildcon Private has been constructing the road.
Kishanganj police station said that after receiving the information, he had asked the company officials to take precautionary measures. Thereafter, the company has erected temporary barricades on both sides of the stretch where cracks had developed.